In the case of plastering of external walls, specific steps should be followed, which are listed as follows:
- As the first step, surveying instruments should be used for alignment and fixing level pegs on the walls.
- ย As the second step, take off the projections from the wall surfaces and clean them to the core.
- The first coat of mortar filling is put up to 15mm on the surface.
- To increase plaster bonding on the concrete wall, cement paste should be used on top of the concrete surfaces.
- A width between the walls and beams will be made by cutting it with the help of grinders after the plastering of the wall surface. It is filled with weather sealant.